How do we replace the concrete or pavers on our HOA pool deck?

By OurHOA · General information · Revised

How an HOA board replaces a pool deck: finding the cause, TX, FL and CO deck rules, slope and slip resistance, the coping joint, bid lines, timeline and owner notice.

Part of the HOA board handbook: vendors, projects and upkeep.

The short answer

Find out why the deck failed before anyone prices a new one. Then write one scope that sets the finish, the slope, the drains and the joint at the coping, call the health and building departments, and schedule the work for the off-season. Most deck failures are water failures: puddles where the slab settled, loose coping, a crack that froze and lifted a trip edge. A new deck poured over the same soft base and the same dead drains will fail the same way. Pool rules differ by state, county and city, and your declaration and bylaws decide who can approve the spending, so treat this as a planning guide and not as legal advice.

Diagnose the old deck first

Walk the deck with a concrete or pool contractor who is not bidding the job, or pay one for a written report. Hose down the whole deck and wait 20 minutes. Chalk around every puddle. A long crack parallel to the coping usually means the deck and the pool shell move separately and nobody left a proper joint between them. On paver decks, look for sunken or rocking pavers and pavers creeping outward where the edge restraint failed. The report should give the cause of each problem, say whether the base is sound, and say whether the deck drains still carry water. Lifting a few settled panels, grinding trip edges, resealing joints and flushing drains can buy several years. If the base is washing out or the slab is broken in many places, replace it and put the reason in the minutes.

What the deck rules say in TX, FL and CO

Texas. The state pool rules in 25 TAC chapter 265, subchapter L, adopt the 2021 International Swimming Pool and Spa Code for construction, alteration, renovation and repair of commercial pools (265.181(b) and (c)). Section 306 of that code sets the deck rules. Decks and coping must be slip resistant and cleanable. The steepest allowed slope is 1/2 inch per foot. The minimum depends on the surface: 1/8 inch per foot for textured hand-finished concrete, 1/4 inch for exposed aggregate, and 3/8 inch for brick-set or travertine pavers at a public pool. Twenty minutes after the water stops, no puddle may be deeper than 1/8 inch. Section 406 requires a slip-resistant surface within 4 feet of the water. Section 265.183(b) lets a minor repair follow the standard in place when the pool was built, so ask the city building department and local health authority in writing which standard applies to a full replacement. Afterward, 265.194(s) bars standing water on the deck. Florida. Section 454.1.3.1 of the Florida Building Code governs public pool wet decks. It requires concrete or another nonabsorbent material with a smooth, slip-resistant finish, prohibits wood decks, and sets a slope of 2 to 4 percent, with 1 percent allowed for pavers. Textured finishes with pits deeper than 3/16 inch are prohibited, and the wet deck must be at least 4 feet wide and unobstructed. Under section 514.03, anyone modifying a public pool must apply to the Department of Health before getting a building permit. The Brevard County office takes modifications on form DH 4159 with plans and no fee. Ask your county office whether a deck job counts. The department's resurfacing form also warns that deck alterations must keep the wet deck as originally approved or meet the current Florida accessibility code. Section 514.0115 exempts pools serving associations of 32 or fewer units from most state supervision, but the building permit still applies. Colorado. The state rule, 5 CCR 1003-5, exempts a private pool used only by residents and their guests. Its public pool standard still makes a good yardstick: 5 feet of unobstructed deck, a non-slip surface with no puddles, and no deck drain serving more than 400 square feet. Call the county health and city building departments and note who you spoke to.

Concrete, overlay or pavers

Pick the surface before you bid, or have every bidder price the same alternates on one form. A broom or textured concrete slab is the plain choice and needs the least slope. Exposed aggregate needs twice the slope under the ISPSC table. Pavers can be lifted and reset when the base settles, but they need a firm base, an edge restraint, joint sand that gets topped up, and 3/8 inch per foot of slope at a Texas public pool. An overlay on sound concrete costs less than a new slab, but on a moving slab it cracks along the old lines. Attach the product's slip resistance data and the manufacturer's installation instructions to the contract. Florida's code requires installation to those instructions, and the document is how you hold the installer to it. Walk on a wet sample board barefoot before the vote. Light colors stay cooler than dark ones, which owners will notice the first July afternoon.

The joint at the coping and other bid lines

The joint between the new deck and the pool coping decides whether the coping survives. ISPSC section 306.7 requires that isolation joint to be watertight and built so deck movement does not damage the coping or its mortar bed, and it requires a joint wherever new deck meets existing concrete. Write the joint detail and the sealant product into the scope. Loose or cracked coping is cheapest to reset while the deck is torn out, so price it per linear foot, and if the pool finish is due within a few years, our guide on how to plan an HOA pool resurfacing project covers doing both in one closure. The rest of the scope should list demolition and haul-off, a unit price per cubic yard for replacing bad base soil (nobody knows the amount until the slab is up), the slope plan and drain locations, control joint layout, secured access covers over valves under the deck (306.9), and resetting the depth and no-diving markers. Texas 265.190(d) requires deck no-diving markers to be slip resistant, at least 4 inches tall and within 18 inches of the water's edge. Say where saw slurry and wash water go. Not into the pool, and not into the storm drain. Saw cutting concrete throws silica dust, and OSHA's rule at 29 CFR 1926.1153 lists saws with a built-in water feed as the control and requires a written exposure control plan that covers keeping other people away. Ask for that plan in the bid. Our guide on how to write an HOA request for proposal covers the bid form and site walk.

Money, bids and a sample timeline

In Florida, section 720.3055 requires competitive bids when a contract exceeds 10 percent of the association's total annual budget, including reserves. In Texas, Property Code 209.0052(c) requires a bid process for service contracts over $50,000. In Colorado, follow the declaration, the bylaws and any procurement policy the board has adopted. A workable schedule for a spring reopening: 10 months out, get the diagnosis report and compare it with the reserve balance for the deck. Eight months out, choose the surface, write the scope and make the regulator calls. Six months out, send the request for proposal with one site walk for all bidders and 30 days to respond. Five months out, put the bid sheet in the board packet and vote on the contract and the funding. Four months out, notify owners while the contractor files the health department application where one applies and pulls the permit. Get in writing how many days the concrete or sealant must cure before furniture goes back, and in Colorado, the contractor's minimum temperature for placing concrete. Before the final payment, repeat the hose test: 20 minutes after the water stops, no puddle deeper than 1/8 inch. Then get the inspections, walk the punch list, and send the reserve study provider the date and cost.

Wording for the motion and the owner notice

Motion: 'Moved to approve the contract with [contractor] to replace the pool deck with [surface] for $[amount] under the bid dated [date], plus a contingency of up to $[amount] for base soil, drain and coping repairs at the unit prices in that bid, paid from the pool deck reserve, with [director] authorized to approve change orders within the contingency and required to report each one at the next board meeting.' Decide at a properly noticed board meeting unless your documents allow another method. If reserves fall short, check your declaration and state law before choosing a special assessment or loan. Owner notice, sent four months out, again two weeks before work starts, and posted at the gate: 'The pool will close on [date] so the deck can be replaced and is scheduled to reopen on [date]. The cost of $[amount] comes from the reserve fund for this work, so there is no special assessment. The pool yard will be locked during construction. Please keep children away from the work area.' Texas 265.194(j) requires keeping users out and posting a closed sign on the gates while a pool is under renovation. Lock the gate, and if the contractor removes a fence section for access, require a temporary barrier the same day.

Mistakes that bring the puddles back

Pouring new concrete on the same washed-out base because nobody priced soil replacement. Butting the new slab tight against the coping, so the next freeze or settlement cracks it. Choosing a deep-textured finish that fails Florida's 3/16-inch pit rule, or a dark one that burns feet in August. Laying pavers without an edge restraint. Forgetting the no-diving and depth markers until the inspector finds them. Paying the last draw before the hose test. Skipping the reserve study update, so next year's budget keeps saving for a deck you already replaced.

Sources

These guides are general education for HOA boards and residents, not legal, tax, or financial advice. Rules vary by state and by your community's governing documents - check with a professional for your situation.